The bridge which is part of the New Double-Track High Speed Railway Line connecting Athens and Thessaloniki, passes over a valley 70m deep and has a total length of 404.8m consisting of three simply supported tied arches (126.85+151.10+126.85), making it the longest steel arch bridge in the Balkans.

The bridge was constructed using the incremental launching method.

 

Our role:

  • Detailed Design of all temporary structures (temporary piers, retaining walls)
  • Detailed Design of the incremental launching procedure assembly yard and launching systems
  • Seismic isolation design
  • Construction Engineering
  • BIM model/Fabrication drawings